Hanam-si, Hakamcheon Stream Maintenance Construction Groundbreaking Resident Briefing Session

Reduced Travel Distance Between Hagam Village and Wirye
Hagamcheon Stream Maintenance Project Targeted for Completion in December 2025
New Hagam 1 Bridge Scheduled for Completion in First Half of 2025

Gyeonggi Hanam City (Mayor Lee Hyun-jae) held a residents' briefing session on the 28th to explain the construction plans and schedule for the 'Hak-am Stream Maintenance Project,' the biggest long-cherished project of the residents of Gamidong and Hakam-dong, and sought the understanding and cooperation of local residents regarding any inconveniences that may occur during the construction.

Hanam-si, Hakamcheon Stream Maintenance Construction Groundbreaking Resident Briefing Session Lee Hyun-jae, Mayor of Hanam City, explained the construction plan and schedule related to the commencement of the 'Hakamcheon Maintenance Project,' the biggest long-cherished project of residents in Gamidong and Hakamdong, to the residents on the 28th. Provided by Hanam City

The residents of Hakam Village have experienced inconvenience as they had to pass through Songpa-gu to commute to Wirye New Town due to the development of the Wirye District. In addition, the undeveloped Hakam Stream posed a risk of flooding during rainy weather.


Accordingly, Hanam City is promoting the 'Hakam Stream Maintenance Project,' which involves maintaining 0.58 km out of the 0.85 km of Hakam Stream by constructing 1,068 meters of embankments and revetments, and establishing the new Hakam 1 Bridge to allow direct passage from Hakam Village to Wirye New Town.

Hanam-si, Hakamcheon Stream Maintenance Construction Groundbreaking Resident Briefing Session Hakamcheon Plan View (Draft). Provided by Hanam City

The project cost for the construction is 11.9 billion KRW, fully funded by LH (Korea Land and Housing Corporation), with Hanam City managing the construction. The Hakam Stream Maintenance Project is scheduled to begin in November this year and aims to be completed by December 2025, with the new Hakam 1 Bridge expected to be completed in the first half of 2025.


On this day, Mayor Lee Hyun-jae attended the residents' briefing session to explain the construction plans and schedule for the new Hakam 1 Bridge and the stream maintenance work, and to ask for understanding regarding any inconveniences that may arise during the construction.


Mayor Lee Hyun-jae emphasized, "I deeply thank the residents who have endured inconveniences and waited for a long time," and added, "Hanam City will continue to do its best to create a safe and pleasant stream environment."