Proven Once Again: Capability in Marine Plant Installation, Commissioning, and Process Management Demonstrated
Hanwha Ocean (CEO President Kim Hee-chul) successfully achieved first oil production on the 15th, two weeks ahead of schedule, for a fixed offshore oil production facility it constructed.
This once again demonstrated Hanwha Ocean's marine plant process management capabilities.
Fixed crude oil production facility installed in the Al-Shaheen oil field area. Provided by Hanwha Ocean
The fixed offshore oil production facility, ordered by Qatar NOC (North Oil Company) in 2021, completed its construction process at the Geoje plant in July and departed for the Al-Shaheen oil field in Qatar, the world's largest offshore oil region.
After about 20 days of sailing, the facility arrived on site and successfully completed various piping and electrical connection works between the topside, jacket, and interconnection bridge, as well as internal equipment and system commissioning over 3.5 months. It achieved first oil production two weeks earlier than planned.
The first oil production is significant as it was conducted safely after preventing marine pollution and securely connecting the facility, marking the start of initial test production. This indicates that full-scale commercial production is now possible. With this early success, Hanwha Ocean has once again proven its technology and competitiveness as a high value-added, high-tech marine plant manufacturer at the world’s highest level.
In particular, Qatar is expected to actively order fixed offshore oil and gas production facilities over the coming years. This achievement is anticipated to have a positive impact on future business activities in the Middle East region.
Philippe Levy, Head of Hanwha Ocean’s Marine Business Division, stated, “To manage this installation project, Hanwha Ocean and the client formed a one-team structure to ensure smooth communication and rapid decision-making. Through this, we secured quality and safety and received praise as a successful marine plant management model due to the swift work.”
Especially through this achievement, Hanwha Ocean expects to further accelerate its transformation into an EPCIO (Engineering, Procurement, Construction, Installation, and Operation) solution provider.
Hanwha Ocean and NOC officials are taking a commemorative photo at the fixed oil production facility installed in the Al-Shaheen oil field area. Photo by Hanwha Ocean
© The Asia Business Daily(www.asiae.co.kr). All rights reserved.